For the South Mud Data Centre Rehab, Project scope with increasing the
data center capacity by allowing more cooling and humidification capability
to maintain the cold and hot isles at the desired design temperature, also
provide alternate cooling system in case of failure in the primary cooling
system.
Worked on the project from the Schematic phase all the way to the
Construction phase, responsible for calculations, design, equipment sizing
and selection, specifications, coordination with other disciplines and
consultants