For the La Cienga high school Central Plant Rehab project, changing the
heating system in the central plant that is serving water source heat pumps,
scope was to replace the existing un-efficient steam boiler and heat
exchanger system with a hot water boiler which is integrated in the same
loop where the cooling tower exists.
Worked on the project from the Schematic phase to the Construction
phase.
Responsible for site investigation, defining the demolition scope,
calculations, design, equipment sizing and selection, specifications,
coordination with other disciplines and consultants.